2018/10/13
Duration: 240 min.
Starts at: 22:00 GMT
Ends at: 02:00 GMT
Status: Completed
Software maintenance for server s803.sureserver.com Our system administrators scheduled a software maintenance on server s803.sureserver.com.

The maintenance will occur as follows:
Maintenance start time: Oct 13, 2018, 22:00 GMT
Maintenance end time: Oct 14, 2018, 02:00 GMT
Expected service outage: up to 120 minutes

The purpose of the maintenance is to complete a hardware upgrade.
2018/10/12
Duration: 120 min.
Starts at: 22:00 GMT
Ends at: 00:00 GMT
Status: Completed
Hardware maintenance for server s801.sureserver.com Our system administrators scheduled a hardware maintenance on server s801.sureserver.com.

The maintenance will occur as follows:
Maintenance start time: Oct 12, 2018, 22:00 GMT
Maintenance end time: Oct 13, 2018, 00:00 GMT
Expected service outage: up to 15 minutes

The purpose of the maintenance is to migrate the server to another machine.
2018/10/06
Duration: 60 min.
Starts at: 08:00 GMT
Ends at: 09:00 GMT
Status: Completed
Software maintenance at the CenturyLink datacenter (USA) Our System Administrators will perform a kernel upgrade on servers in the datacenter in USA.

Maintenance start time: Oct 06, 2018, 04:00 EDT
Maintenance end time: Oct 06, 2018, 05:00 EDT
Expected service outage: up to five minutes

The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.
2018/10/06
Duration: 120 min.
Starts at: 07:00 GMT
Ends at: 09:00 GMT
Status: Completed
Hardware maintenance for server s467.sureserver.com Our system administrators scheduled a hardware maintenance for server s467.sureserver.com.

The maintenance will occur as follows:
Maintenance start time: Oct 6, 2018, 03:00 EDT
Maintenance end time: Oct 6, 2018, 05:00 EDT
Expected service outage: up to 30 minutes

The purpose of the maintenance is to complete a hardware upgrade.
2018/10/05
Duration: 60 min.
Starts at: 20:30 GMT
Ends at: 21:30 GMT
Status: Completed
Software maintenance at the Neterra (Europe) datacenter Our System Administrators will perform a kernel upgrade on servers in the datacenter in Neterra (Europe).

Maintenance start time: Oct 05, 2018, 23:30 EET
Maintenance end time: Oct 06, 2018, 00:30 EET
Expected service outage: up to five minutes

The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.
2018/10/05
Duration: 60 min.
Starts at: 18:30 GMT
Ends at: 19:30 GMT
Status: Completed
Software maintenance at the iAdvantage (Hong Kong) datacenter Our System Administrators will perform a kernel upgrade on servers in the datacenter in Hong Kong.

Maintenance start time: Oct 05, 2018, 02:30 HKT
Maintenance end time: Oct 05, 2018, 03:30 HKT
Expected service outage: up to five minutes

The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.
2018/10/03
Duration: 60 min.
Starts at: 08:00 GMT
Ends at: 09:00 GMT
Status: Completed
Software maintenance at the CenturyLink datacenter (USA) Our System Administrators will perform a kernel upgrade on servers in the datacenter in USA.

Maintenance start time: Oct 03, 2018, 04:00 EDT
Maintenance end time: Oct 03, 2018, 05:00 EDT
Expected service outage: up to five minutes

The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.
2018/10/01
Duration: 30 min.
Starts at: 19:30 GMT
Ends at: 20:00 GMT
Status: Completed
Kernel Upgrades in Hong Kong Our System Administrators will perform a kernel upgrade on servers in the datacenter in Hong Kong. The upgrade procedure requires a server reboot, and brief outages (up to five minutes) may occur.
2018/09/29
Duration: 120 min.
Starts at: 07:00 GMT
Ends at: 09:00 GMT
Status: Completed
Maintenance for server server273.com at the CenturyLink datacenter (USA) Our system administrators scheduled a maintenance server server273.com at the CenturyLink datacenter (USA).

The maintenance will occur as follows:

Maintenance start time: Sep 29, 2018, 03:00 EDT
Maintenance end time: Sep 29, 2018, 05:00 EDT
Expected service outage: up to five minutes

The purpose of the maintenance is perform hardware repairs that require a server reboot.
2018/09/27
Duration: 120 min.
Starts at: 22:00 GMT
Ends at: 00:00 GMT
Status: Completed
Hardware maintenance for server s802.sureserver.com The maintenance will occur as follows:
Maintenance start time: Sep 27, 2018, 22:00 UTC
Maintenance end time: Sep 28, 2018, 00:01 UTC
Expected service outage: up to 20 minutes

The purpose of the maintenance is to complete a hardware upgrade.